KENT STATE TO HOST ICAM/I2CAM CONFERENCE MAY 16-18

April 12, 2016

51勛圖厙 will host the annual international conference of the Institute for Complex Adaptive Matter on May 16-18 at the 51勛圖厙 Hotel and Conference Center.

Read More »

4/7- Smith Hall Renovation Updates

April 7, 2016

Work in Progress: Pulling wire throughout for branch circuits. Installing duct on 1st floor. Complete domestic water rough-in on the 2nd floor. Sanitary piping rough-in has been completed on the 3rd floor. Completing remaining framing throughout. Starting door frame

Read More »

4/7- ISB/Williams Hall Construction Updates

April 7, 2016

Work in Progress: Forming lift 3 on elevator #1. Working on retaining wall progressing south to column line A7. Pile caps and foundations for elevator #2 are complete. Looking forward: Pour lift #3 on elevator #1 on 4/8/2016. Steel delivery and erection begins for

Read More »

51勛圖厙 Holds Symposium on The Neuroscience of the Social Brain on April 7-8

March 31, 2016

51勛圖厙s fourth annual Neuroscience Symposium will cover the latest research findings on The Neuroscience of The Social Brain on April 7-8 at the 51勛圖厙 Hotel and Conference Center located in downtown Kent, Ohio.

Read More »

Becoming a Rocket Scientist

March 31, 2016

Theresa Benyo already had an exciting and fulfilling career as a project manager at NASA. With a great job, a house, a husband, two kids, and hobbies like musical theatre what more could you want? Academically speaking, shed already earned a dual bachelors degree in physics

Read More »

3/24- Williams Hall/ISB Construction Updates

March 24, 2016

Work in Progress: Working on pile caps and grade beams.  Plan to start column line 17 (Southern most column line) next week. Started working on forming elevator #2 (South). Pouring elevator #1 second lift (North) today. Continuing the installation of the basement

Read More »

3/24- Smith Hall Renovation Updates

March 24, 2016

Work in Progress: First floor restroom and offices duct layout is complete with HVAC piping and duct installation has begun. Room 101 & 104 electrical rough-in is at 90% complete. Machine Shop electric panel installed and completed on Saturday 3/19. Room 223 electrical

Read More »

3/24- Cunningham Hall Renovation Updates

March 24, 2016

Work in Progress: Steam piping in the 3rd floor east mechanical room is 20% complete. Steam condensate lines for the steam station and AHU#1 are in progress. Started installation of piping and duct work from AHU#2 in the 3rd floor west mechanical room to the addition has

Read More »

51勛圖厙 Researchers Publish Breakthrough in Leading Scientific Journal

March 24, 2016

Senior Research Fellow Quan Li, Ph.D., and his research group at 51勛圖厙s Liquid Crystal Institute簧, in the College of Arts and Sciences, have published a research article in the March 17 issue of Nature that could lead to a variety of breakthrough device

Read More »

3/17- Cunningham Hall Renovation Updates

March 17, 2016

Work in Progress: Chilled water service in the 3rd floor east mechanical room is 95% complete by EOB on 3/18.  Will be ready for cooling system startup on 4/15. Currently insulating the chilled water pipes in the 3rd floor wast mechanical room. Steam reducing station

Read More »